Solved by a verified expert :Grade Details – All Questions
Question 1. Question
: The Monitoring and Controlling
Process Group interacts with ¬__________ Process Group(s): all

the Initiating

the Planning

the Executing

Points Received: 2 of 2
Comments:

Question 2. Question
: Change requests may include
the following except:

 corrective action.

preventive action.

key performance indicators.

updates.

Points Received: 0 of 2
Comments:

Question 3. Question
: Which is not an input to the
Integrated Change Control Process?

Change requests

Change control tools

Organizational Process Assets

Project Management Plan

Points Received: 0 of 2
Comments:

Question 4. Question
: A __________ is used to
document changes that occur during the project.

change baseline

change log

change request

change control board

Points Received: 0 of 2
Comments:

Question 5. Question
: For closure documents, the
customer acceptance documentation is an output from the:

Control Scope Process.

Control Quality Process.

Validate Scope Process.

Close Project or Phase Process.

Points Received: 0 of 2
Comments:

Question 6. Question
: Managing changes to
deliverables is performed by the __________ Process.

Validate Scope

Control Scope

Perform Integrated Change Control

Monitor and Control Project Work

Points Received: 2 of 2
Comments:

Question 7. Question
: Projects with overlapping
phases are:

less risky than a project with sequential
phases.

more risky than a project with sequential
phases.

neither more nor less risky than a project
with sequential phases.
more risky if a subsequent phase progresses
before accurate information is available from the previous phase.

Points Received: 2 of 2
Comments:

Question 8. Question
: Perform Quality Assurance is
in the __________ Process Group:

Executing

Planning

Closing

Monitoring and Controlling

Points Received: 0 of 2
Comments:

Question 9. Question
: Data flows from the Perform
Integrated Change Control Process to:

Control Scope.

Control Quality.

All of the above.

Control Cost.

Points Received: 0 of 2
Comments:

Question 10. Question
: Data flows from the Close
Project or Phase Process to the:

Enterprise/organization.

Validate Scope.

Close Procurements.

Develop Project Management Plan.

Points Received: 0 of 2