Solved by verified expert :1. Which of the
following is considered a primary report in an MRP system?␣
(p. 602)
.
2. Which of the
following is the net requirement using an MRP program if the gross requirement
is 1,250 and the inventory on hand is 50?
(p. 605)

3. Which of the
following is the net requirement using an MRP program if the gross requirement
is 1,000 and the inventory on hand is 500?
(p. 605)

4. Which of the
following is the planned-order release using an MRP program if the gross
requirement is 5,000, inventory on hand is 1,200 and planned receipts are
800?

(p. 605)

5. Which of the
following is the planned-order release using an MRP program if the gross
requirement is 670 and the inventory on hand is 600?
(p. 605)

6. Which of the
following can be used for lot sizing in an MRP system?␣
(p. 611)

7. Which of the
following is not a lot sizing technique used in MRP systems?␣
(p. 611)